Harry
Seidler: The rolling waveform of the building, which rises from
the Darling Harbour towards Harris Street and the Ultimo ridge, has
been created to reflect and reinforce the topography of the Pyrmont
Ultimo peninsula. The waveform also has obvious aquatic symbology.
ULTIMO
AQUATIC CENTRE (UAC) APPROVAL TO LODGE THE DEVELOPMENT APPLICATION
AT SYDNEY HARBOUR FORESHORE AUTHORITY (SHFA) FOR THE REVISED UAC SCHEME
BACKGROUND
Subsequent
to a report dated 21 December 2001 by the former Lord Mayor Frank Sartor
on the UAC and Public Space Design Competition advising
of the jury deliberation and conclusion, Council had resolved that the
project proceed to Design Development and the proposed land transfer
from SHFA to the City be expedited.
On 30
April 2002 the City resolved that it would not invite tenders for the
selection of an architect for the UAC project and that authority be
delegated to the General Manager to finalise in consultation with the
Lord Mayor, the terms of contract engaging Harry Seidler & Associated
(HAS) as the project Architect, with authority to councils attorney
to execute all contracts.
Council
on 16 December 2002 endorsed the shortlist of building contractors and
approved that the shortlisted building contractors be invited to tender.
At an Extraordinary Meeting of Council on 10 March 2003, it was resolved
that the UAC land be classified as operational land.
The consultant
team advised Council that due to current market price pressures, the
budget needed to be reviewed in consideration of the then present scheme.
With this advice and management recommendation, Council resolved on
31 March 2003 that in respect of Capital Works Reallocation, a revised
budget of $27 million was approved for the UAC.
In April
2003 the Citys updated programme was to call for tenders from
select building contractors in early July 2003 and to execute contracts
with the successful tenderer for the UAC at the end of September 2003.
City Development
& Projects in June 2003 initiated its appraisal of the overall project
brief, to review needs and space requirements, including simplifying
the overall scheme to a 50m pool, program/hydrotherapy pool with children
leisure access, change rooms and amenities with approximately 63 carparking
bays. This review arose out of:
- the
consultant teams identification of broader industry and market
risks to tender prices likely to be submitted and at the same time
the construction estimate was approaching the original total development
budget of $25 million;
- consideration
that some sporting facilities now provided at the Ultimo Community
Centre (UCC) situated across Harris Street from the UAC appeared under
utilised. The gymnasium function proposed for UAC could be rationalized
with the UCC facilities, with UCC facilities enhanced to meet future
demand of this facility.
The City
is committed to provide a quality swimming pool facility similar in
finishes and components to the earlier pool. Moreover, better rationalized
in its planning and functionality, efficient in that the management
of the program/hydrotherapy pool could also meet the needs of children
swimming classes, and would meet the aims of the master plan for the
area.
This revised
scheme was presented by HAS and assessed by City officers and directors
of Asset Management & Compliance and City Development and Projects
on 25 July 2003. Subsequent to his the City instructed HAS to develop
this scheme for the purposes of a DA submission preceding the calling
of tenders.
PROPOSAL
That Council
approve the lodgement of the DA to SHFA for the revised UAC scheme.
OPTIONS
That Council
accept the above recommendations and approve the lodgement of the DA
to SHFA for the revised UAC scheme. This is the preferred option.
That Council
reject the above recommendations and not lodge the DA for the revised
scheme hence tender on the existing scheme. This is not preferred as
it may be an over capitalization of the Citys facility and not
be cost effective.
CRITICAL
DATES
The critical
date of 9 September 2003 is when City Development & Projects intends
to submit a DA to SHFA.
The requirements
of the Tripartite Deed with Australand and SHFA provide these two other
parties with rights to exercise Lot 23 and Lot 3 options respectively,
should the City not achieve substantial commencement of the Aquatic
Centre Development Works by 30 June 2005 and 30 December 2006, respectively.
POLICY
IMPLICATIONS
The revised
scheme has been discussed with and designs provided to the signatories
of the Tripartite Deed between SHFA, Australand and the City.
FINANCIAL
IMPLICATIONS/FUNDING CERTIFICATES
The financial
implications are:
- that
the revised UAC scheme would be expected to be less than the original
budget;
- through
the Capital Works Review Committee the budget has been reduced to
$24 million from the $27 million approved at Council resolution of
31 March 2003 on Capital Works Reallocation. The $3 million difference
has been allocated to the Capital Works contingency fund.
CONSULTATION
City Development
& Projects Unit has consulted with Asset Management & Compliance
(AM&C). As a result of consultation AM&C is in agreement that
the revised scheme be progressed initially with the DA then with the
calling of tenders.
RELEVANT
LEGISLATION
The Local
Government Act, 1993.
CONCLUSION
City Development
& Projects in June 2003 initiated its appraisal of the overall project
brief, to review needs and space requirements, including simplifying
the overall scheme to a 50m pool, program/hydrotherapy pool with children
leisure access, change rooms and amenities with approximately 63 carparking
bays. This review arose out of:
- the
consultant teams identification of broader industry and market
risks to tender prices likely to be submitted and at the same time
the construction estimate was approaching the original total development
budget of $25 million;
- consideration
that some sporting facilities now provided at the Ultimo Community
Centre (UCC) situated across Harris Street from the UAC appeared under
utilised. The gymnasium function proposed for UAC could be rationalized
with the UCC facilities, with UCC facilities enhanced to meet future
demand of this facility.
The City
is committed to provide a quality swimming pool facility similar in
finishes and components to the earlier pool. Moreover, better rationalized
in its planning and functionality, efficient in that the management
of the program/hydrotherapy pool could also meet the needs of children
swimming classes, and would meet the aims of the master plan for the
area.
City Development
& Projects and Asset Management & Compliance staff have reviewed
the scheme and are in agreement that this revised scheme is improved
as a result of the strategic review of the UAC against the UCC. Both
City Development & Projects and Asset Management and Compliance
are in agreement that this revised scheme should be progressed initially
with a DA followed by tender.
RECOMMENDATION
That arising
from consideration of a report by the Senior Project Manager to Council
on 8 September 2003, on the UAC Approval to lodge the DA at SHFA
for the revised UAC scheme, it be resolved:
- Council
approve the lodgement of the DA at SHFA for the revised UAC scheme;
and
- Councils
attorney be authorised to execute all necessary documentation.
(SGD)
CUMARAN SIVA (9338)
Senior
Project Manager
Bob
Walker